| ID |
Task Name
|
Duration |
Start |
Finish |
Resource Names |
% Complete |
| 1 |
Tabone Street - Design
|
20 days |
Thu 30/06/05 |
Sun 31/07/05 |
|
90% |
| 2 |
Tabone Street - Subdivision Design
|
15 days |
Mon 19/09/05 |
Sat 8/10/05 |
|
80% |
| 3 |
Keppel Terrace - Design
|
10 days |
Fri 29/07/05 |
Sun 14/08/05 |
|
95% |
| 4 |
John St - Design
|
10 days |
Fri 29/07/05 |
Sun 14/08/05 |
|
75% |
| 5 |
Armstrong Rd - Design
|
20 days |
Thu 30/06/05 |
Mon 1/08/05 |
|
90% |
| 6 |
Canal Creek - Design
|
10 days |
Fri 1/07/05 |
Fri 15/07/05 |
|
100% |
| 7 |
Artillary Rd - Design
|
23.75 days |
Mon 12/09/05 |
Sun 13/11/05 |
[50%]
|
60% |
| 8 |
Werribee Ck - Design
|
10 days |
Mon 5/12/05 |
Sat 17/12/05 |
|
0% |
| 9 |
Atkinson rd (Sandy Ck Bridge) - Design
|
10 days |
Fri 1/07/05 |
Fri 15/07/05 |
|
100% |
| 10 |
Stoney Ck Rd - Creek No. 1 - Design
|
5 days |
Mon 6/02/06 |
Fri 10/02/06 |
|
0% |
| 11 |
Stoney Ck Rd - Creek No. 2 - Design
|
5 days |
Mon 13/02/06 |
Mon 20/02/06 |
|
0% |
| 12 |
Limpus Ave - boat ramp - Design
|
37 days |
Fri 1/07/05 |
Sun 28/08/05 |
|
90% |
| 13 |
Coowonga Rd - Cawarral Ck - Design
|
10 days |
Mon 5/12/05 |
Sat 31/12/05 |
|
0% |
| 14 |
Cowoonga Road-min std seal
|
19 days |
Fri 1/07/05 |
Fri 29/07/05 |
|
100% |
| 15 |
Emu Park - Street Lighting Conduits
|
85 days |
Mon 1/08/05 |
Fri 2/12/05 |
|
85% |
| 16 |
Emu Park Bus Interchange-Civil
|
30 days |
Mon 7/11/05 |
Sat 17/12/05 |
|
23% |
| 17 |
Emu Park - General Maintenance
|
9 days |
Tue 3/01/06 |
Sat 14/01/06 |
|
0% |
| 18 |
Emu Park Stage 1-Civil
|
70 days |
Mon 7/11/05 |
Tue 28/02/06 |
|
5% |
| 19 |
Emu Park Stage 3B-Civil
|
10 days |
Wed 1/03/06 |
Tue 14/03/06 |
|
0% |
| 20 |
Emu Park Stage 2-Civil
|
40 days |
Wed 15/03/06 |
Sat 20/05/06 |
|
0% |
| 21 |
Coowonga Area - General Maintenance
|
9 days |
Mon 22/05/06 |
Fri 2/06/06 |
|
0% |
| 22 |
Mt Chalmers Area - General Maintenance
|
9 days |
Sat 3/06/06 |
Thu 22/06/06 |
|
0% |
| 23 |
Artillary rd-min std seal & drainage
|
45 days? |
Mon 26/06/06 |
Fri 25/08/06 |
|
0% |
| 24 |
Emu Park Bus Interchange-Landscaping
|
30 days |
Tue 22/11/05 |
Tue 17/01/06 |
|
0% |
| 25 |
Emu Park Stage 1-Landscaping
|
35 days |
Wed 18/01/06 |
Thu 9/03/06 |
|
0% |
| 26 |
Emu Park Stage 3B-Landscaping
|
8 days |
Wed 17/05/06 |
Thu 25/05/06 |
|
0% |
| 27 |
Emu Park Stage 2-Landscaping
|
35 days |
Mon 29/05/06 |
Mon 24/07/06 |
|
0% |
| 28 |
Strow Street-Drainage
|
11 days |
Fri 1/07/05 |
Mon 18/07/05 |
|
100% |
| 29 |
Emu Park-Underground Power
|
85 days |
Tue 19/07/05 |
Mon 21/11/05 |
|
100% |
| 30 |
Limpus Ave-boat ramp
|
40 days |
Fri 10/03/06 |
Tue 16/05/06 |
|
0% |
| 31 |
Area A - General Maintenance
|
18 days |
Fri 1/07/05 |
Thu 28/07/05 |
|
100% |
| 32 |
Mt Rae Road-gravel resheet with seal
|
6 days |
Wed 13/07/05 |
Wed 20/07/05 |
|
100% |
| 33 |
Cliff Street-min std seal
|
3 days |
Thu 21/07/05 |
Tue 26/07/05 |
|
100% |
| 34 |
Adelaide Park Road-private works
|
4 days |
Wed 27/07/05 |
Mon 1/08/05 |
|
90% |
| 35 |
Tabone Street-road & drainage
|
160 days |
Tue 2/08/05 |
Wed 5/04/06 |
|
50% |
| 36 |
Tabone Street - Subdivision works
|
110 days |
Mon 17/10/05 |
Tue 4/04/06 |
|
30% |
| 37 |
Mary Street Drainage
|
10 days |
Mon 21/11/05 |
Sat 3/12/05 |
|
0% |
| 38 |
Hidden Valley Rd-gravel resheet with seal
|
9 days |
Mon 22/08/05 |
Thu 1/09/05 |
|
100% |
| 39 |
White Rock Rd - Culverts
|
2 days |
Mon 5/09/05 |
Tue 6/09/05 |
|
100% |
| 40 |
Bungandarra Area - General Maintenance
|
9 days |
Mon 9/01/06 |
Wed 18/01/06 |
|
0% |
| 41 |
John St-K&C and bus parking & Private
works for school
|
40 days |
Mon 5/12/05 |
Tue 14/02/06 |
|
0% |
| 42 |
Ivey Street West - Drainage Improvements
|
10 days? |
Mon 9/01/06 |
Thu 19/01/06 |
|
0% |
| 43 |
Lane behind Queen Street
|
10 days? |
Mon 23/01/06 |
Mon 6/02/06 |
|
0% |
| 44 |
Old Byfield Road(Mt Rae-Lake Mary)-gravel resheet
|
8 days |
Wed 15/02/06 |
Sat 25/02/06 |
|
0% |
| 45 |
Keppel Terrace
|
15 days? |
Mon 27/02/06 |
Mon 20/03/06 |
|
0% |
| 46 |
RMPC - Byfield Area
|
9 days |
Tue 21/03/06 |
Thu 30/03/06 |
|
0% |
| 47 |
Armstrong Rd-new construction
|
70 days? |
Mon 3/04/06 |
Thu 27/07/06 |
|
0% |
| 48 |
Bondoola Area - General Maintenance
|
14 days |
Mon 24/04/06 |
Tue 16/05/06 |
|
0% |
| 49 |
Milman & Caves Areas - General Maintenance
|
18 days |
Fri 1/07/05 |
Thu 28/07/05 |
|
100% |
| 50 |
Plover Drive-Council Subdivision
|
55 days |
Fri 1/07/05 |
Fri 23/09/05 |
|
100% |
| 51 |
Pine Mountain Rd-gravel resheet with seal
|
15 days |
Mon 15/08/05 |
Tue 6/09/05 |
|
100% |
| 52 |
Canal Creek-creek crossing
|
30 days |
Mon 26/09/05 |
Sat 5/11/05 |
|
100% |
| 53 |
Greenlake rd/Artillary rd-gravel resheet
|
14 days |
Mon 7/11/05 |
Thu 24/11/05 |
|
65% |
| 54 |
Etna Creek Rd-gravel resheet & seal
|
20 days |
Mon 28/11/05 |
Mon 9/01/06 |
|
0% |
| 55 |
Milman Area - General Maintenance
|
18 days |
Tue 10/01/06 |
Thu 2/02/06 |
|
0% |
| 56 |
Caves Area - General Maintenance
|
18 days |
Mon 6/02/06 |
Tue 28/02/06 |
|
0% |
| 57 |
Werribee Ck - 10.3m of RCBC
|
12 days? |
Wed 6/09/06 |
Thu 21/09/06 |
|
0% |
| 58 |
Raspberry Ck Rd - for ADF
|
100 days? |
Wed 1/03/06 |
Tue 8/08/06 |
|
0% |
| 59 |
Raspbery Ck Rd Area - General Maintenance
|
20 days |
Wed 9/08/06 |
Tue 5/09/06 |
|
0% |
| 60 |
Stanage Bay Rd - General Maintenance
|
41 days |
Mon 11/07/05 |
Fri 9/09/05 |
|
100% |
| 61 |
Stanage Bay rd-gravel resheet
|
46 days |
Fri 1/07/05 |
Fri 9/09/05 |
|
100% |
| 62 |
Apis Ck Rd (for Main Roads) gravel resheet
|
10 days |
Mon 12/09/05 |
Mon 26/09/05 |
|
100% |
| 63 |
Atkinson Rd (Sandy Ck Bridge)
|
33 days |
Tue 27/09/05 |
Thu 10/11/05 |
|
100% |
| 64 |
Nickel Rd - General Maintenance
|
1 day |
Mon 14/11/05 |
Mon 14/11/05 |
|
100% |
| 65 |
Coorumba Road - General Maintenance
|
9 days |
Tue 15/11/05 |
Fri 25/11/05 |
|
50% |
| 66 |
Glenprairie Area - General Maintenance
|
9 days |
Mon 28/11/05 |
Wed 7/12/05 |
|
0% |
| 67 |
Kooltandra/Stoodleigh Rds - General Maintenance
|
12 days |
Thu 8/12/05 |
Tue 10/01/06 |
|
0% |
| 68 |
Ogmore Area - General Maintenance
|
9 days |
Wed 11/01/06 |
Mon 23/01/06 |
|
0% |
| 69 |
Ogmore Connection - RMPC
|
10 days |
Tue 24/01/06 |
Tue 7/02/06 |
|
0% |
| 70 |
Anglewood Rd - General Maintenance
|
15 days |
Tue 24/01/06 |
Mon 13/02/06 |
|
0% |
| 71 |
Apis Ck Rd - RMPC
|
28 days |
Tue 14/02/06 |
Fri 24/03/06 |
|
0% |
| 72 |
Apis Ck/Clifton Area - General Maintenance
|
15 days |
Mon 6/03/06 |
Fri 24/03/06 |
|
0% |
| 73 |
Marlborough/Bruce Hwy Area - General Maintenance
|
9 days |
Sat 25/03/06 |
Thu 6/04/06 |
|
0% |
| 74 |
Atkinson Rd/Yaamba Area - General Maintenace
|
13 days |
Fri 7/04/06 |
Fri 5/05/06 |
|
0% |
| 75 |
Rasberry Ck Rd - for ADF
|
40 days? |
Sat 6/05/06 |
Mon 10/07/06 |
|
0% |
| 76 |
Stanage Bay Rd - General Maintenace
|
27 days |
Tue 11/07/06 |
Wed 16/08/06 |
|
0% |
| 77 |
Area D - General Maintenace
|
20 days |
Fri 1/07/05 |
Mon 1/08/05 |
|
100% |
| 78 |
Hawke st-min std seal
|
4 days |
Wed 6/07/05 |
Tue 12/07/05 |
|
100% |
| 79 |
Higson st-min std seal
|
4 days |
Wed 13/07/05 |
Mon 18/07/05 |
|
100% |
| 80 |
Joskeliegh/Keppel Sands rds-intersection upgrade
|
9 days |
Tue 19/07/05 |
Mon 1/08/05 |
|
95% |
| 81 |
Hill St-widenening for Main Roads
|
84 days |
Tue 2/08/05 |
Fri 2/12/05 |
|
85% |
| 82 |
Pattison St-drainage for Main Roads
|
15 days? |
Mon 21/11/05 |
Mon 12/12/05 |
|
0% |
| 83 |
Thompson Pt/Nerimbra - General Maintenance
|
9 days |
Wed 30/11/05 |
Mon 12/12/05 |
|
0% |
| 84 |
Sleipner Rd-gravel resheet
|
15 days |
Tue 13/12/05 |
Mon 16/01/06 |
|
0% |
| 85 |
Mackay Rd-intersection for Main Roads
|
35 days? |
Tue 17/01/06 |
Wed 8/03/06 |
|
0% |
| 86 |
Stoney Ck Rd - Creek No. 1 - 8.6m of RCBC
|
10 days? |
Thu 9/03/06 |
Wed 22/03/06 |
|
0% |
| 87 |
Stoney CK Rd - Creek No. 2 - 6.8m of RCBC
|
8 days? |
Thu 23/03/06 |
Mon 3/04/06 |
|
0% |
| 88 |
Coowonga Rd - Cawarral Ck - 10.2m of RCBC
|
20 days? |
Fri 2/06/06 |
Fri 7/07/06 |
|
0% |
| 89 |
Scenic Hwy-Rosslyn Bay Intersection
|
35 days? |
Tue 4/04/06 |
Thu 1/06/06 |
|
0% |
| 90 |
QT Bus Set DOWNS
|
30 days? |
Thu 11/05/06 |
Sat 1/07/06 |
|
0% |
| 91 |
Thompson Point rd-gravel resheet with seal
|
23 days |
Mon 10/07/06 |
Wed 9/08/06 |
|
0% |
| 92 |
Hidden Valley Rd - Seal
|
1 day |
Mon 5/09/05 |
Mon 5/09/05 |
|
100% |
| 93 |
Mt Rae Rd - Seal
|
2 days |
Thu 21/07/05 |
Mon 25/07/05 |
|
50% |
| 94 |
Pine Mountain Rd - Seal
|
1 day |
Wed 7/09/05 |
Wed 7/09/05 |
|
100% |
| 95 |
Thompson Pt Rd - Seal
|
4 days |
Thu 10/08/06 |
Tue 15/08/06 |
|
0% |
| 96 |
Main Roads Reseal Prep Works
|
25 days |
Mon 17/10/05 |
Fri 18/11/05 |
|
40% |
| 97 |
Asphalt reseals
|
5 days |
Sat 11/02/06 |
Thu 16/02/06 |
|
0% |
| 98 |
Slurry seals
|
5 days |
Mon 6/02/06 |
Fri 10/02/06 |
|
0% |
| 99 |
Reseals
|
5 days |
Mon 20/02/06 |
Fri 24/02/06 |
|
0% |
| 100 |
BanWan Bridge - Design & Construct
|
235 days |
Tue 3/01/06 |
Tue 19/12/06 |
|
0% |
| 101 |
Alligator Ck Bridge - Design & Construct
|
235 days |
Tue 3/01/06 |
Tue 19/12/06 |
|
0% |